Public Discussions about Kelowna Development Projects
Pejamu about UBCO Downtown
May 01, 2024
One72 Concretes Instagram story(as of May 1) has footage of a big pour so it appears the backfill is done? Not sure if they are going to drive piles through all the backfill and concrete unless they did that before they started filling, anybody know?
Pejamu about Movala
Apr 28, 2024
I guess as they get higher the floors will get smaller and construction will move faster?
Steady speed of 1 poor in 2 months. Level 7 on the south tower. Cladding in progress for levels 1-4.

Jim Kelowna |construction update at Alma on Abbott
Apr 26, 2024

Jim Kelowna |construction update at Water Street by the Park
Apr 26, 2024
Jack B about 1110 Lawson Ave
Apr 25, 2024

Jim Kelowna |construction update at Movala
Apr 19, 2024

Jim Kelowna |construction update at The Ledge on Lakeshore
Apr 19, 2024
Jack B |construction update at Caban
Apr 14, 2024
Jack B about UBCO Downtown
Apr 10, 2024
The construction work continues, good news.

Construction resumes on UBCO’s downtown Kelowna campus, despite evacuations
Construction has resulted in four neighbouring properties being evacuated
Jack B
Apr 09, 2024
Been quiet on the development news this week, anyone with construction updates?
Emry Formworks |construction update at Aqua
Apr 06, 2024

Izzy about UBCO Downtown
Apr 03, 2024
My hope is that the project will continue, as it is an amazing opportunity to revive the downtown core of Kelowna. Watching for updates from the engineers, UBC has the money and opportunities to make it right.
I am surprised that the city is quiet on this and engineers are not providing any solutions after months of trouble. It's unclear how this will affect the future of high-rise developments in Kelowna, or if it will impact just that particular part of downtown.
I hope projects like Water By The Park succeed, so people don't blame all high-rises, but rather this instance, due to the large underground parkade.

Jim Kelowna about UBCO Downtown
Apr 03, 2024
I am surprised that the city is quiet on this and engineers are not providing any solutions after months of trouble. It's unclear how this will affect the future of high-rise developments in Kelowna, or if it will impact just that particular part of downtown.
I hope projects like Water By The Park succeed, so people don't blame all high-rises, but rather this instance, due to the large underground parkade.
Jack B about UBCO Downtown
Mar 31, 2024
This is very sad that it continue to cause problems, as I would like this project to succeed. There has been no updates on construction, which they promised, however it creates more problems and I start to worry they reconsider the whole thing.

Kelowna subsidized apartments evacuated due to neighbouring UBC Okanagan construction - Kelowna News
Residents were escorted out of the building on Bertram Street just before 2 p.m. by members of the Kelowna Fire Department and city staff.
Pejamu about Dilworth Centre
Mar 30, 2024
C-Lovers is relocating to the Capri Mall as well.
True, good it's finally moving forward. As for the tenants, it was recently announced JYSK is returning to Kelowna to Orchard Plaza (instead of Rooms + Spaces).
Overall about building sizes, I am sad that a lot of those projects in Kelowna are just 6 storeys. Feels like it's going to be a problem for the city in 20 years, after it will run out of space.