Nov 19, 2023
According to a new article on Castanet Office will open up in Q1 2024 and the Residential tower some time in the summer.

Two Bernard Avenue towers should be complete by next summer - Kelowna News
From the untrained eye, two new towers rising above Bernard Avenue appear almost ready to occupy.

Jim Kelowna about Landmark 7
Nov 18, 2023
There is a chance to check the tower from the inside this Christmas:
Following the Light Up, attendees are encouraged to head to the 19th floor of Landmark 7, where they will encounter a winter wonderland hosting over 30 vendors from the Kelowna Farmers' and Crafters' Market

Kelowna to illuminate with annual Tree of Hope Light Up - Kelowna News
The City of Kelowna will once again shine brightly this holiday season with the Stober Group's annual Tree of Hope Light Up.

Jim Kelowna |construction update at UBCO Downtown
Nov 17, 2023

Jim Kelowna |construction update at 450 Parc
Nov 17, 2023

Jim Kelowna |construction update at 1333 Bertram St
Nov 17, 2023

Jim Kelowna |construction update at Mara at Pandosy Village
Nov 17, 2023
Jack B about 1333 Bertram St
Nov 16, 2023
Looks like construction is finally starting with some machinery seen on the site.
Jack B |construction update at 1605 GORDON DRIVE
Nov 15, 2023
Jack B |construction update at Water Street by the Park
Nov 14, 2023
Jack B about Bertram Bernard Block
Nov 13, 2023
The Office Block crane was removed in October, finishing the exterior :)
Jack B |construction update at Nolita
Nov 13, 2023

Jim Kelowna about 515 Rutland
Nov 05, 2023
Dayana L. about Savoy on Clement
Nov 04, 2023
No progress seen on the construction or excavation of Savoy.
Jack B |construction update at Aqua
Nov 04, 2023
Jack B |construction update at Nolita
Oct 24, 2023